PHOTOS: Published Photos of this Project are Prohibited Due to a Non Disclosure Agreement.

Weyerhaeuser TPM Paper Machine

Location: Kingsport, TN
Client: Weyerhaeuser Industries, Inc.
Owner: Weyerhaeuser Industries, Inc.
Services: Structural Steel/Equipment Setting

Description:

LPR erected a 9,000 ton multi-structure addition to existing plant. Peak manpower reached 80 plus Ironworkers over a 2 year period. The site was extremely congested at the working facility. Weyerhaeuser added a Paper Machine Bldg, Bleach Plant and Recovery Boiler to LPR’s scope of work. Our company worked hand in hand with the Weyerhaeuser Construction Team to build the new plant with technology that will quadruple the output of any existing Paper Machine Building in the USA.

Reference:
Greg Duvall
Construction Manager North America
Weyerhaeuser Industries, Inc.

L.P.R. Construction Co. | 1171 Des Moines Avenue | Loveland, Colorado 80537