![]() Rollover images to enlarge below. |
Northstar Phase III
Location: Truckee, CA
General Contractor: G.E. Johnson Construction Co.
Fabricator: Cives Steel Company
Tons: 1600 tons
Description
Winter in the mountains brings good skiing but tough construction! The 3 building lodge at Northstar had to be erected during the winter. Battling cold and snow and tight site conditions, L.P.R. was still able to maintain schedule and erect a quality project on this complex project.